These dates may be a little off because I am just going off what I remember and not looking up every date but they are really close, maybe only off by a day 2 at most.
1/5 - Offer Made
1/9 - Offer Accepted
1/12 - Submitted for RoFR
1/25 - Passed RoFR
2/6 - I Received Closing Docs
2/11 - Mailed off Closing Docs
2/14 - MV Title Co. received closing docs.
2/16 - Closed
I guess there was also the Estopple process sometime between 1/25 and 2/6 but I do not know dates for that. Title company was pretty quite during that time and I didn't ask any questions about it really.